High filling rate of R.W concereting has been Carried By BFS one-side shuttering methods.
In order to operate the retaining walls of the project with a 3.5 meter height, the one-sided formwork of the metal modular formwork system, with a diagonal Bracing retaining system which was made from the soldiers of the modular formwork system, was designed and manufactured and operated at BFS company in Dubai, UAE. Taking the high filling rate of the concrete in the project into consideration, these soldiers were financially beneficial for the project in addition to their usage both as a diagonal supporting and also a vertical straightener of formworks.